Building Project

Ariel View of new PreK-12 School Front View of new PreK-12 School

 

 

The Owners Project Manager for the Holbrook Public Schools Feasibility is SMMA 

SMMA Contacts:

Joel G. Seeley, AIA, LEED AP BD+C
COO | Executive Vice President
SMMA | Symmes Maini & McKee Associates
Architecture | Engineering | Interior Design | Planning
1000 Massachusetts Avenue, Cambridge, MA  02138
www.smma.com

Voting Members:

 
Daniel F. Moriarty, PSBC Chair, Member with Local Licensing Board
James Day Vice Chair, Member with architectural experience
Matthew Moore, Board of Selectmen Chair
Beth Tolson, School Committee Member
TBD, Member with Education Experience
Thomas Taylor, Member with Industry Experience
Peter Mahoney, Finance Committee Member
Scott R. Towne, Member-At-Large
Fred White, Member with Industry Experience
Stephanie Trowbridge, Member-At-Large

 
 
Non-Voting Members:
 
Julie S. Hamilton, Holbrook Public Schools Superintendent of Schools
Patricia Lugo, Holbrook Public Schools Procurement Administrator
Timothy Gordon, Town Administrator
Julie Hamilton, Building Principal
Michael Bolger, Director of Facilities
Joel Seeley, SMMA, OPM

   PROJECT INFORMATION   

Commence Construction
Fall 2015

 

Open School
August 2017

 
Complete Fields and Site Work
Summer 2018
 

 

 